Construction at Merewether continues to progress with strong momentum, with key structural works advancing steadily throughout February. Major groundwork remains on track, supporting the coordinated delivery of the next phase of construction.
During the month, detailed excavation and piling works continued across site, alongside ongoing installation of the capping beam and shoring wall to further strengthen the structural framework. Levelling works at Hole 3 were also successfully completed, with turfing and irrigation now underway, reflecting the steady progress being achieved across multiple areas of the project.
As we move through March, works will remain focused on advancing the capping beam and shoring wall, with excavation continuing in parallel to prepare the site for the next stages of structural construction. Turfing and irrigation at Hole 3 are scheduled for completion later this month, bringing this area to its finished level.